PassEveryTest

White Card Practice Test (CPCWHS1001) 2026:第2套练习测试

White Card Practice Test (CPCWHS1001) 练习测试第2套(共2套):再练35道题,附答案和解释。

  • 职场安全
  • 澳大利亚
  • 60道题
  • 核对于2026年10月11日
  1. 第1题,共35题

    When must a SWMS be prepared?
    显示答案

    答案: C. Before high risk construction work starts

    The PCBU must make sure a SWMS is prepared before the high risk construction work starts.

  2. 第2题,共35题

    High risk construction work is not being done the way the SWMS says. What must happen?
    显示答案

    答案: A. The work must stop immediately, or as soon as it is safe, and the SWMS is reviewed

    Work must stop and not restart until it can be done in line with the SWMS, which should be reviewed.

  3. 第3题,共35题

    Construction work with a risk of a person falling more than how far is high risk construction work?
    显示答案

    答案: A. 2 metres

    Work with a risk of a fall of more than 2 metres is high risk construction work and needs a SWMS.

  4. 第4题,共35题

    Work in or near a trench deeper than what depth is high risk construction work?
    显示答案

    答案: D. 1.5 metres

    Work in or near a shaft or trench with an excavated depth of more than 1.5 metres is high risk construction work.

  5. 第5题,共35题

    Which of these jobs is high risk construction work that needs a SWMS?
    显示答案

    答案: D. Work that is likely to disturb asbestos

    Work that involves, or is likely to involve, disturbing asbestos is high risk construction work.

  6. 第6题,共35题

    Which task is on the list of high risk construction work?
    显示答案

    答案: D. Work on or near energised electrical installations

    Work on or near energised electrical installations or services is on the high risk construction work list.

  7. 第7题,共35题

    Which of these is classed as high risk construction work?
    显示答案

    答案: B. Work in an area where powered mobile plant is moving

    Work in an area with movement of powered mobile plant, such as excavators and loaders, is high risk construction work.

  8. 第8题,共35题

    For construction projects worth how much must a principal contractor be appointed?
    显示答案

    答案: A. $250,000 or more

    A principal contractor must be appointed for construction projects valued at $250,000 or more.

  9. 第9题,共35题

    What must a principal contractor prepare in writing before work on the project begins?
    显示答案

    答案: A. A WHS management plan

    The principal contractor must prepare a written WHS management plan before work begins and make it available to workers.

  10. 第10题,共35题

    What must the principal contractor's site signs show?
    显示答案

    答案: D. The principal contractor's contact details

    Principal contractors must put up signs showing their contact details so people can reach them.

  11. 第11题,共35题

    You have a white card and start at a new site. What else should you receive?
    显示答案

    答案: C. A site-specific induction about that site's hazards and procedures

    The white card is general. Each workplace also gives a site-specific induction about its own safety issues.

  12. 第12题,共35题

    What is a toolbox talk?
    显示答案

    答案: C. A short pre-start meeting about the work, its hazards and controls

    Toolbox talks or pre-start meetings help builders, subcontractors and workers share safety information and consult.

  13. 第13题,共35题

    Who can represent workers when a PCBU consults them about health and safety?
    显示答案

    答案: D. A health and safety representative (HSR)

    Workers can be represented in consultation by an elected health and safety representative.

  14. 第14题,共35题

    Where do you find information about a hazardous chemical's dangers, safe handling and first aid?
    显示答案

    答案: B. Its safety data sheet (SDS)

    White card training covers the purpose of safety data sheets, SWMS and job safety analyses.

  15. 第15题,共35题

    What is the best way to stop people falling from the edge of a roof?
    显示答案

    答案: D. Install edge protection such as a guardrail system

    A physical barrier like a roof perimeter guardrail stops falls. It is more reliable than signs or instructions.

  16. 第16题,共35题

    What does a residual current device (RCD), or safety switch, do?
    显示答案

    答案: D. Cuts the power fast to reduce the risk of electric shock

    RCDs are an engineering control that reduce the risk of electric shock.

  17. 第17题,共35题

    You uncover sheeting that you think may contain asbestos. What should you do?
    显示答案

    答案: C. Stop work, do not disturb it, and tell your supervisor

    Do not disturb suspected asbestos. Stop, keep others away and report it so it can be checked and managed.

  18. 第18题,共35题

    How does asbestos harm people?
    显示答案

    答案: A. Breathing in its fibres can cause asbestosis, lung cancer and mesothelioma

    Asbestos fibres breathed into the lungs can cause serious diseases, often many years later.

  19. 第19题,共35题

    Who can remove asbestos?
    显示答案

    答案: C. Only people with special training and a licence

    Safe Work Australia says you need special training and a licence to remove asbestos.

  20. 第20题,共35题

    Which task can release harmful respirable crystalline silica dust?
    显示答案

    答案: D. Dry cutting concrete, brick or stone

    Cutting, grinding, drilling or sanding stone, concrete and masonry, especially dry, can release silica dust that causes silicosis.

  21. 第21题,共35题

    Which control reduces silica dust when cutting with power tools?
    显示答案

    答案: B. Water suppression (wet cutting) or on-tool dust extraction

    Wet cutting, on-tool extraction or local exhaust ventilation capture dust at the source. A respirator is also needed.

  22. 第22题,共35题

    What has applied to engineered stone in most of Australia since 1 July 2024?
    显示答案

    答案: A. Work on or with it is banned, except for stone installed before the ban

    A national prohibition on engineered stone applies from 1 July 2024 in most jurisdictions.

  23. 第23题,共35题

    Which PPE helps protect against excessive noise?
    显示答案

    答案: B. Earplugs or earmuffs

    Hearing protection such as earplugs or earmuffs reduces exposure to excessive noise.

  24. 第24题,共35题

    Which is an engineering control for manual handling risk?
    显示答案

    答案: C. Using a hoist to lift heavy tools and materials

    Mechanical aids like hoists reduce the risk of musculoskeletal injuries from lifting.

  25. 第25题,共35题

    How can workers on foot be kept safe from mobile plant?
    显示答案

    答案: C. Separate the plant work zone with physical barriers and a traffic management plan

    Physical barriers, exclusion zones and traffic management plans keep people and mobile plant apart.

  26. 第26题,共35题

    A sign shows a red circle with a red diagonal line over a black symbol. What does it mean?
    显示答案

    答案: D. Prohibition: you must not do this

    Prohibition signs use a red circle and slash to show an action that is not permitted.

  27. 第27题,共35题

    What does a sign with a white symbol on a solid blue circle mean?
    显示答案

    答案: B. You must do this (mandatory)

    Blue circle signs are mandatory signs, such as 'hard hats must be worn'.

  28. 第28题,共35题

    What does a yellow sign with a black triangle usually mean?
    显示答案

    答案: B. Warning of a hazard that is not likely to be life-threatening

    Warning signs have a black triangle on yellow, for example a forklift hazard sign.

  29. 第29题,共35题

    A sign has the word DANGER in white on a red oval inside a black rectangle. What does it mean?
    显示答案

    答案: B. There is a hazard that is likely to be life-threatening

    Danger signs warn of hazards likely to be life-threatening, such as high voltage.

  30. 第30题,共35题

    Which signs are green with white symbols or text?
    显示答案

    答案: C. Emergency information signs, such as exits and first aid

    Emergency information signs, showing exits, safety equipment and first aid, are green with white text or symbols.

  31. 第31题,共35题

    A worker is seriously injured on site. When must the WHS regulator be notified?
    显示答案

    答案: D. Immediately after becoming aware of it

    Deaths, serious injuries or illnesses and dangerous incidents must be notified to the regulator immediately.

  32. 第32题,共35题

    After a notifiable incident, what must be done with the incident scene?
    显示答案

    答案: C. Leave it undisturbed until an inspector arrives or gives directions, except to help people or make it safe

    The scene must not be disturbed, except to help an injured person, make the site safe or follow police or inspector directions.

  33. 第33题,共35题

    A tool falls from a scaffold but misses everyone. What should you do?
    显示答案

    答案: B. Report it as a near miss so the cause can be fixed

    Near misses and dangerous occurrences should be reported so hazards are fixed before someone is hurt.

  34. 第34题,共35题

    You reasonably believe a task would expose you to a serious risk from an immediate hazard. What can you do?
    显示答案

    答案: B. Stop or refuse the work and tell the PCBU as soon as practicable

    Workers can cease unsafe work in these cases, but must tell the PCBU and stay available for suitable alternative work.

  35. 第35题,共35题

    Why must workers not come to site affected by alcohol or drugs?
    显示答案

    答案: D. It can put themselves and others at serious risk