White Card Practice Test (CPCWHS1001) 2026: Test próbny 2

Test próbny 2 z 2 – White Card Practice Test (CPCWHS1001): kolejne pytania z odpowiedziami i wyjaśnieniami (liczba pytań: 35).

  • BHP
  • Australia
  • Pytania: 60
  • Sprawdzono 11 października 2026
  1. Pytanie 1 z 35

    When must a SWMS be prepared?
    Pokaż odpowiedź

    Odpowiedź: C. Before high risk construction work starts

    The PCBU must make sure a SWMS is prepared before the high risk construction work starts.

  2. Pytanie 2 z 35

    High risk construction work is not being done the way the SWMS says. What must happen?
    Pokaż odpowiedź

    Odpowiedź: A. The work must stop immediately, or as soon as it is safe, and the SWMS is reviewed

    Work must stop and not restart until it can be done in line with the SWMS, which should be reviewed.

  3. Pytanie 3 z 35

    Construction work with a risk of a person falling more than how far is high risk construction work?
    Pokaż odpowiedź

    Odpowiedź: A. 2 metres

    Work with a risk of a fall of more than 2 metres is high risk construction work and needs a SWMS.

  4. Pytanie 4 z 35

    Work in or near a trench deeper than what depth is high risk construction work?
    Pokaż odpowiedź

    Odpowiedź: D. 1.5 metres

    Work in or near a shaft or trench with an excavated depth of more than 1.5 metres is high risk construction work.

  5. Pytanie 5 z 35

    Which of these jobs is high risk construction work that needs a SWMS?
    Pokaż odpowiedź

    Odpowiedź: D. Work that is likely to disturb asbestos

    Work that involves, or is likely to involve, disturbing asbestos is high risk construction work.

  6. Pytanie 6 z 35

    Which task is on the list of high risk construction work?
    Pokaż odpowiedź

    Odpowiedź: D. Work on or near energised electrical installations

    Work on or near energised electrical installations or services is on the high risk construction work list.

  7. Pytanie 7 z 35

    Which of these is classed as high risk construction work?
    Pokaż odpowiedź

    Odpowiedź: B. Work in an area where powered mobile plant is moving

    Work in an area with movement of powered mobile plant, such as excavators and loaders, is high risk construction work.

  8. Pytanie 8 z 35

    For construction projects worth how much must a principal contractor be appointed?
    Pokaż odpowiedź

    Odpowiedź: A. $250,000 or more

    A principal contractor must be appointed for construction projects valued at $250,000 or more.

  9. Pytanie 9 z 35

    What must a principal contractor prepare in writing before work on the project begins?
    Pokaż odpowiedź

    Odpowiedź: A. A WHS management plan

    The principal contractor must prepare a written WHS management plan before work begins and make it available to workers.

  10. Pytanie 10 z 35

    What must the principal contractor's site signs show?
    Pokaż odpowiedź

    Odpowiedź: D. The principal contractor's contact details

    Principal contractors must put up signs showing their contact details so people can reach them.

  11. Pytanie 11 z 35

    You have a white card and start at a new site. What else should you receive?
    Pokaż odpowiedź

    Odpowiedź: C. A site-specific induction about that site's hazards and procedures

    The white card is general. Each workplace also gives a site-specific induction about its own safety issues.

  12. Pytanie 12 z 35

    What is a toolbox talk?
    Pokaż odpowiedź

    Odpowiedź: C. A short pre-start meeting about the work, its hazards and controls

    Toolbox talks or pre-start meetings help builders, subcontractors and workers share safety information and consult.

  13. Pytanie 13 z 35

    Who can represent workers when a PCBU consults them about health and safety?
    Pokaż odpowiedź

    Odpowiedź: D. A health and safety representative (HSR)

    Workers can be represented in consultation by an elected health and safety representative.

  14. Pytanie 14 z 35

    Where do you find information about a hazardous chemical's dangers, safe handling and first aid?
    Pokaż odpowiedź

    Odpowiedź: B. Its safety data sheet (SDS)

    White card training covers the purpose of safety data sheets, SWMS and job safety analyses.

  15. Pytanie 15 z 35

    What is the best way to stop people falling from the edge of a roof?
    Pokaż odpowiedź

    Odpowiedź: D. Install edge protection such as a guardrail system

    A physical barrier like a roof perimeter guardrail stops falls. It is more reliable than signs or instructions.

  16. Pytanie 16 z 35

    What does a residual current device (RCD), or safety switch, do?
    Pokaż odpowiedź

    Odpowiedź: D. Cuts the power fast to reduce the risk of electric shock

    RCDs are an engineering control that reduce the risk of electric shock.

  17. Pytanie 17 z 35

    You uncover sheeting that you think may contain asbestos. What should you do?
    Pokaż odpowiedź

    Odpowiedź: C. Stop work, do not disturb it, and tell your supervisor

    Do not disturb suspected asbestos. Stop, keep others away and report it so it can be checked and managed.

  18. Pytanie 18 z 35

    How does asbestos harm people?
    Pokaż odpowiedź

    Odpowiedź: A. Breathing in its fibres can cause asbestosis, lung cancer and mesothelioma

    Asbestos fibres breathed into the lungs can cause serious diseases, often many years later.

  19. Pytanie 19 z 35

    Who can remove asbestos?
    Pokaż odpowiedź

    Odpowiedź: C. Only people with special training and a licence

    Safe Work Australia says you need special training and a licence to remove asbestos.

  20. Pytanie 20 z 35

    Which task can release harmful respirable crystalline silica dust?
    Pokaż odpowiedź

    Odpowiedź: D. Dry cutting concrete, brick or stone

    Cutting, grinding, drilling or sanding stone, concrete and masonry, especially dry, can release silica dust that causes silicosis.

  21. Pytanie 21 z 35

    Which control reduces silica dust when cutting with power tools?
    Pokaż odpowiedź

    Odpowiedź: B. Water suppression (wet cutting) or on-tool dust extraction

    Wet cutting, on-tool extraction or local exhaust ventilation capture dust at the source. A respirator is also needed.

  22. Pytanie 22 z 35

    What has applied to engineered stone in most of Australia since 1 July 2024?
    Pokaż odpowiedź

    Odpowiedź: A. Work on or with it is banned, except for stone installed before the ban

    A national prohibition on engineered stone applies from 1 July 2024 in most jurisdictions.

  23. Pytanie 23 z 35

    Which PPE helps protect against excessive noise?
    Pokaż odpowiedź

    Odpowiedź: B. Earplugs or earmuffs

    Hearing protection such as earplugs or earmuffs reduces exposure to excessive noise.

  24. Pytanie 24 z 35

    Which is an engineering control for manual handling risk?
    Pokaż odpowiedź

    Odpowiedź: C. Using a hoist to lift heavy tools and materials

    Mechanical aids like hoists reduce the risk of musculoskeletal injuries from lifting.

  25. Pytanie 25 z 35

    How can workers on foot be kept safe from mobile plant?
    Pokaż odpowiedź

    Odpowiedź: C. Separate the plant work zone with physical barriers and a traffic management plan

    Physical barriers, exclusion zones and traffic management plans keep people and mobile plant apart.

  26. Pytanie 26 z 35

    A sign shows a red circle with a red diagonal line over a black symbol. What does it mean?
    Pokaż odpowiedź

    Odpowiedź: D. Prohibition: you must not do this

    Prohibition signs use a red circle and slash to show an action that is not permitted.

  27. Pytanie 27 z 35

    What does a sign with a white symbol on a solid blue circle mean?
    Pokaż odpowiedź

    Odpowiedź: B. You must do this (mandatory)

    Blue circle signs are mandatory signs, such as 'hard hats must be worn'.

  28. Pytanie 28 z 35

    What does a yellow sign with a black triangle usually mean?
    Pokaż odpowiedź

    Odpowiedź: B. Warning of a hazard that is not likely to be life-threatening

    Warning signs have a black triangle on yellow, for example a forklift hazard sign.

  29. Pytanie 29 z 35

    A sign has the word DANGER in white on a red oval inside a black rectangle. What does it mean?
    Pokaż odpowiedź

    Odpowiedź: B. There is a hazard that is likely to be life-threatening

    Danger signs warn of hazards likely to be life-threatening, such as high voltage.

  30. Pytanie 30 z 35

    Which signs are green with white symbols or text?
    Pokaż odpowiedź

    Odpowiedź: C. Emergency information signs, such as exits and first aid

    Emergency information signs, showing exits, safety equipment and first aid, are green with white text or symbols.

  31. Pytanie 31 z 35

    A worker is seriously injured on site. When must the WHS regulator be notified?
    Pokaż odpowiedź

    Odpowiedź: D. Immediately after becoming aware of it

    Deaths, serious injuries or illnesses and dangerous incidents must be notified to the regulator immediately.

  32. Pytanie 32 z 35

    After a notifiable incident, what must be done with the incident scene?
    Pokaż odpowiedź

    Odpowiedź: C. Leave it undisturbed until an inspector arrives or gives directions, except to help people or make it safe

    The scene must not be disturbed, except to help an injured person, make the site safe or follow police or inspector directions.

  33. Pytanie 33 z 35

    A tool falls from a scaffold but misses everyone. What should you do?
    Pokaż odpowiedź

    Odpowiedź: B. Report it as a near miss so the cause can be fixed

    Near misses and dangerous occurrences should be reported so hazards are fixed before someone is hurt.

  34. Pytanie 34 z 35

    You reasonably believe a task would expose you to a serious risk from an immediate hazard. What can you do?
    Pokaż odpowiedź

    Odpowiedź: B. Stop or refuse the work and tell the PCBU as soon as practicable

    Workers can cease unsafe work in these cases, but must tell the PCBU and stay available for suitable alternative work.

  35. Pytanie 35 z 35

    Why must workers not come to site affected by alcohol or drugs?
    Pokaż odpowiedź

    Odpowiedź: D. It can put themselves and others at serious risk

    Not working under the influence of drugs or alcohol is one of the safe work practices taught in white card training.