White Card Practice Test (CPCWHS1001) 2026: Teste prático 2
Teste prático 2 de 2 — White Card Practice Test (CPCWHS1001): mais 35 perguntas com respostas e explicações.
-
Pergunta 1 de 35
Mostrar resposta
Resposta: C. Before high risk construction work starts
The PCBU must make sure a SWMS is prepared before the high risk construction work starts.
-
Pergunta 2 de 35
Mostrar resposta
Resposta: A. The work must stop immediately, or as soon as it is safe, and the SWMS is reviewed
Work must stop and not restart until it can be done in line with the SWMS, which should be reviewed.
-
Pergunta 3 de 35
Mostrar resposta
Resposta: A. 2 metres
Work with a risk of a fall of more than 2 metres is high risk construction work and needs a SWMS.
-
Pergunta 4 de 35
Mostrar resposta
Resposta: D. 1.5 metres
Work in or near a shaft or trench with an excavated depth of more than 1.5 metres is high risk construction work.
-
Pergunta 5 de 35
Mostrar resposta
Resposta: D. Work that is likely to disturb asbestos
Work that involves, or is likely to involve, disturbing asbestos is high risk construction work.
-
Pergunta 6 de 35
Mostrar resposta
Resposta: D. Work on or near energised electrical installations
Work on or near energised electrical installations or services is on the high risk construction work list.
-
Pergunta 7 de 35
Mostrar resposta
Resposta: B. Work in an area where powered mobile plant is moving
Work in an area with movement of powered mobile plant, such as excavators and loaders, is high risk construction work.
-
Pergunta 8 de 35
Mostrar resposta
Resposta: A. $250,000 or more
A principal contractor must be appointed for construction projects valued at $250,000 or more.
-
Pergunta 9 de 35
Mostrar resposta
Resposta: A. A WHS management plan
The principal contractor must prepare a written WHS management plan before work begins and make it available to workers.
-
Pergunta 10 de 35
Mostrar resposta
Resposta: D. The principal contractor's contact details
Principal contractors must put up signs showing their contact details so people can reach them.
-
Pergunta 11 de 35
Mostrar resposta
Resposta: C. A site-specific induction about that site's hazards and procedures
The white card is general. Each workplace also gives a site-specific induction about its own safety issues.
-
Pergunta 12 de 35
Mostrar resposta
Resposta: C. A short pre-start meeting about the work, its hazards and controls
Toolbox talks or pre-start meetings help builders, subcontractors and workers share safety information and consult.
-
Pergunta 13 de 35
Mostrar resposta
Resposta: D. A health and safety representative (HSR)
Workers can be represented in consultation by an elected health and safety representative.
-
Pergunta 14 de 35
Mostrar resposta
Resposta: B. Its safety data sheet (SDS)
White card training covers the purpose of safety data sheets, SWMS and job safety analyses.
-
Pergunta 15 de 35
Mostrar resposta
Resposta: D. Install edge protection such as a guardrail system
A physical barrier like a roof perimeter guardrail stops falls. It is more reliable than signs or instructions.
-
Pergunta 16 de 35
Mostrar resposta
Resposta: D. Cuts the power fast to reduce the risk of electric shock
RCDs are an engineering control that reduce the risk of electric shock.
-
Pergunta 17 de 35
Mostrar resposta
Resposta: C. Stop work, do not disturb it, and tell your supervisor
Do not disturb suspected asbestos. Stop, keep others away and report it so it can be checked and managed.
-
Pergunta 18 de 35
Mostrar resposta
Resposta: A. Breathing in its fibres can cause asbestosis, lung cancer and mesothelioma
Asbestos fibres breathed into the lungs can cause serious diseases, often many years later.
-
Pergunta 19 de 35
Mostrar resposta
Resposta: C. Only people with special training and a licence
Safe Work Australia says you need special training and a licence to remove asbestos.
-
Pergunta 20 de 35
Mostrar resposta
Resposta: D. Dry cutting concrete, brick or stone
Cutting, grinding, drilling or sanding stone, concrete and masonry, especially dry, can release silica dust that causes silicosis.
-
Pergunta 21 de 35
Mostrar resposta
Resposta: B. Water suppression (wet cutting) or on-tool dust extraction
Wet cutting, on-tool extraction or local exhaust ventilation capture dust at the source. A respirator is also needed.
-
Pergunta 22 de 35
Mostrar resposta
Resposta: A. Work on or with it is banned, except for stone installed before the ban
A national prohibition on engineered stone applies from 1 July 2024 in most jurisdictions.
-
Pergunta 23 de 35
Mostrar resposta
Resposta: B. Earplugs or earmuffs
Hearing protection such as earplugs or earmuffs reduces exposure to excessive noise.
-
Pergunta 24 de 35
Mostrar resposta
Resposta: C. Using a hoist to lift heavy tools and materials
Mechanical aids like hoists reduce the risk of musculoskeletal injuries from lifting.
-
Pergunta 25 de 35
Mostrar resposta
Resposta: C. Separate the plant work zone with physical barriers and a traffic management plan
Physical barriers, exclusion zones and traffic management plans keep people and mobile plant apart.
-
Pergunta 26 de 35
Mostrar resposta
Resposta: D. Prohibition: you must not do this
Prohibition signs use a red circle and slash to show an action that is not permitted.
-
Pergunta 27 de 35
Mostrar resposta
Resposta: B. You must do this (mandatory)
Blue circle signs are mandatory signs, such as 'hard hats must be worn'.
-
Pergunta 28 de 35
Mostrar resposta
Resposta: B. Warning of a hazard that is not likely to be life-threatening
Warning signs have a black triangle on yellow, for example a forklift hazard sign.
-
Pergunta 29 de 35
Mostrar resposta
Resposta: B. There is a hazard that is likely to be life-threatening
Danger signs warn of hazards likely to be life-threatening, such as high voltage.
-
Pergunta 30 de 35
Mostrar resposta
Resposta: C. Emergency information signs, such as exits and first aid
Emergency information signs, showing exits, safety equipment and first aid, are green with white text or symbols.
-
Pergunta 31 de 35
Mostrar resposta
Resposta: D. Immediately after becoming aware of it
Deaths, serious injuries or illnesses and dangerous incidents must be notified to the regulator immediately.
-
Pergunta 32 de 35
Mostrar resposta
Resposta: C. Leave it undisturbed until an inspector arrives or gives directions, except to help people or make it safe
The scene must not be disturbed, except to help an injured person, make the site safe or follow police or inspector directions.
-
Pergunta 33 de 35
Mostrar resposta
Resposta: B. Report it as a near miss so the cause can be fixed
Near misses and dangerous occurrences should be reported so hazards are fixed before someone is hurt.
-
Pergunta 34 de 35
Mostrar resposta
Resposta: B. Stop or refuse the work and tell the PCBU as soon as practicable
Workers can cease unsafe work in these cases, but must tell the PCBU and stay available for suitable alternative work.
-
Pergunta 35 de 35
Mostrar resposta
Resposta: D. It can put themselves and others at serious risk
Not working under the influence of drugs or alcohol is one of the safe work practices taught in white card training.