CSCS Test Practice (CITB HS&E Operatives) 2026: Test d’entraînement 4
Test d’entraînement 4 sur 5 pour l’examen « CSCS Test Practice (CITB HS&E Operatives) » : 25 questions supplémentaires avec réponses et explications.
-
Question 1 sur 25
Voir la réponse
Réponse: D. The top three steps
HSE says do not stand or work on the top three steps of a stepladder.
-
Question 2 sur 25
Voir la réponse
Réponse: C. No, never stand a ladder on movable objects
HSE says never stand a ladder on movable objects such as pallets, bricks or vans.
-
Question 3 sur 25
Voir la réponse
Réponse: D. Tie both stiles to a suitable point
Tying both stiles is the first choice. Footing the ladder is the last resort.
-
Question 4 sur 25
Voir la réponse
Réponse: C. Before first use, then at least every 7 days
Scaffolds must also be inspected after anything likely to affect them, such as bad weather or alterations.
-
Question 5 sur 25
Voir la réponse
Réponse: A. Only a competent scaffolder
Scaffolds must be erected, altered and dismantled by competent people. Unauthorised changes can cause collapse or falls.
-
Question 6 sur 25
Voir la réponse
Réponse: A. At least 950 mm
The top guardrail must be at least 950 mm above the working platform.
-
Question 7 sur 25
Voir la réponse
Réponse: C. 470 mm
The gap between the top rail and the intermediate rail must not be more than 470 mm.
-
Question 8 sur 25
Voir la réponse
Réponse: D. To stop people or materials falling off the edge
Toe boards must be suitable and sufficient to prevent people or materials falling.
-
Question 9 sur 25
Voir la réponse
Réponse: A. Someone trained under a scheme such as PASMA
Tower erectors must be competent and trained, and must follow the manufacturer's instructions.
-
Question 10 sur 25
Voir la réponse
Réponse: D. Avoid going on the roof, for example by working from underneath
Fragile roofs can give way without warning. Avoid working on them where possible.
-
Question 11 sur 25
Voir la réponse
Réponse: A. Before use at the start of each shift
Users should do a pre-use check every shift. Detailed inspections are also needed at set intervals.
-
Question 12 sur 25
Voir la réponse
Réponse: C. At the start of each shift
CDM 2015 requires excavations to be inspected at the start of each shift and after events such as a fall of material.
-
Question 13 sur 25
Voir la réponse
Réponse: B. Their weight can make the sides collapse
Loads near the edge can cause collapse. Edge protection and stop blocks also help prevent falls.
-
Question 14 sur 25
Voir la réponse
Réponse: B. Raise the alarm and do not go in unless trained to rescue
Many people who die in confined spaces were trying to rescue others. Only trained rescuers with the right equipment should go in.
-
Question 15 sur 25
Voir la réponse
Réponse: C. Harmful gases or a lack of oxygen
Confined spaces can contain toxic gases or too little oxygen. Work in them needs training and a safe system of work.
-
Question 16 sur 25
Voir la réponse
Réponse: C. So more can be reused or recycled
Separating waste supports the waste hierarchy: reduce, reuse and recycle before disposal.
-
Question 17 sur 25
Voir la réponse
Réponse: A. Reduce the amount of waste you create
Preventing waste comes first, then reuse, recycling, recovery and finally disposal.
-
Question 18 sur 25
Voir la réponse
Réponse: A. Use the spill kit to stop it reaching drains, and report it
Fuel can pollute land and water. Contain it with a spill kit and report it at once.
-
Question 19 sur 25
Voir la réponse
Réponse: D. In bunded containers or on drip trays, away from drains
Secondary containment such as bunds and drip trays catches leaks and spills.
-
Question 20 sur 25
Voir la réponse
Réponse: D. Only in the designated washout area
Concrete washings are harmful to water life. Never let them reach drains or watercourses.
-
Question 21 sur 25
Voir la réponse
Réponse: A. Stop work in that area and report it
Nesting wild birds are protected by law. Report the find so a specialist can advise.
-
Question 22 sur 25
Voir la réponse
Réponse: C. Stop work and report it
Bats and their roosts are protected by law. Work must stop until advice is taken.
-
Question 23 sur 25
Voir la réponse
Réponse: B. Do not disturb it and report it
Japanese knotweed is an invasive plant. Moving or spreading it can break the law.
-
Question 24 sur 25
Voir la réponse
Réponse: C. To cut noise, fumes and fuel waste
Idling engines create noise and air pollution and waste fuel.
-
Question 25 sur 25
Voir la réponse
Réponse: D. Control dust and noise, and keep to the agreed working hours
Dust, noise and mud can harm neighbours and the environment and lead to complaints and enforcement.
Clavier : 1–4 pour répondre, Entrée pour la question suivante.