Frage 1 von 25
Antwort anzeigen
Antwort: D. The top three steps
HSE says do not stand or work on the top three steps of a stepladder.
-
Frage 2 von 25
Antwort anzeigen
Antwort: C. No, never stand a ladder on movable objects
HSE says never stand a ladder on movable objects such as pallets, bricks or vans.
-
Frage 3 von 25
Antwort anzeigen
Antwort: D. Tie both stiles to a suitable point
Tying both stiles is the first choice. Footing the ladder is the last resort.
-
Frage 4 von 25
Antwort anzeigen
Antwort: C. Before first use, then at least every 7 days
Scaffolds must also be inspected after anything likely to affect them, such as bad weather or alterations.
-
Frage 5 von 25
Antwort anzeigen
Antwort: A. Only a competent scaffolder
Scaffolds must be erected, altered and dismantled by competent people. Unauthorised changes can cause collapse or falls.
-
Frage 6 von 25
Antwort anzeigen
Antwort: A. At least 950 mm
The top guardrail must be at least 950 mm above the working platform.
-
Frage 7 von 25
Antwort anzeigen
Antwort: C. 470 mm
The gap between the top rail and the intermediate rail must not be more than 470 mm.
-
Frage 8 von 25
Antwort anzeigen
Antwort: D. To stop people or materials falling off the edge
Toe boards must be suitable and sufficient to prevent people or materials falling.
-
Frage 9 von 25
Antwort anzeigen
Antwort: A. Someone trained under a scheme such as PASMA
Tower erectors must be competent and trained, and must follow the manufacturer's instructions.
-
Frage 10 von 25
Antwort anzeigen
Antwort: D. Avoid going on the roof, for example by working from underneath
Fragile roofs can give way without warning. Avoid working on them where possible.
-
Frage 11 von 25
Antwort anzeigen
Antwort: A. Before use at the start of each shift
Users should do a pre-use check every shift. Detailed inspections are also needed at set intervals.
-
Frage 12 von 25
Antwort anzeigen
Antwort: C. At the start of each shift
CDM 2015 requires excavations to be inspected at the start of each shift and after events such as a fall of material.
-
Frage 13 von 25
Antwort anzeigen
Antwort: B. Their weight can make the sides collapse
Loads near the edge can cause collapse. Edge protection and stop blocks also help prevent falls.
-
Frage 14 von 25
Antwort anzeigen
Antwort: B. Raise the alarm and do not go in unless trained to rescue
Many people who die in confined spaces were trying to rescue others. Only trained rescuers with the right equipment should go in.
-
Frage 15 von 25
Antwort anzeigen
Antwort: C. Harmful gases or a lack of oxygen
Confined spaces can contain toxic gases or too little oxygen. Work in them needs training and a safe system of work.
-
Frage 16 von 25
Antwort anzeigen
Antwort: C. So more can be reused or recycled
Separating waste supports the waste hierarchy: reduce, reuse and recycle before disposal.
-
Frage 17 von 25
Antwort anzeigen
Antwort: A. Reduce the amount of waste you create
Preventing waste comes first, then reuse, recycling, recovery and finally disposal.
-
Frage 18 von 25
Antwort anzeigen
Antwort: A. Use the spill kit to stop it reaching drains, and report it
Fuel can pollute land and water. Contain it with a spill kit and report it at once.
-
Frage 19 von 25
Antwort anzeigen
Antwort: D. In bunded containers or on drip trays, away from drains
Secondary containment such as bunds and drip trays catches leaks and spills.
-
Frage 20 von 25
Antwort anzeigen
Antwort: D. Only in the designated washout area
Concrete washings are harmful to water life. Never let them reach drains or watercourses.
-
Frage 21 von 25
Antwort anzeigen
Antwort: A. Stop work in that area and report it
Nesting wild birds are protected by law. Report the find so a specialist can advise.
-
Frage 22 von 25
Antwort anzeigen
Antwort: C. Stop work and report it
Bats and their roosts are protected by law. Work must stop until advice is taken.
-
Frage 23 von 25
Antwort anzeigen
Antwort: B. Do not disturb it and report it
Japanese knotweed is an invasive plant. Moving or spreading it can break the law.
-
Frage 24 von 25
Antwort anzeigen
Antwort: C. To cut noise, fumes and fuel waste
Idling engines create noise and air pollution and waste fuel.
-
Frage 25 von 25
Antwort anzeigen
Antwort: D. Control dust and noise, and keep to the agreed working hours
Dust, noise and mud can harm neighbours and the environment and lead to complaints and enforcement.