Managers and professionals applying for a Black Manager card or a Qualified Person CSCS card need a pass in the CITB Managers and Professionals HS&E test within the last two years. CITB runs the test: 50 questions in 45 minutes, with at least 45 correct to pass. This is independent practice written for managers, not operatives.
Quick answer
The CITB Health, Safety and Environment (HS&E) test for Managers and Professionals (MAP) has 50 questions. Pass mark: 45 of 50 (90%). Time limit: 45 minutes. It is run by the Construction Industry Training Board (CITB). Practise here for free with 75 questions, each with the answer and an explanation. Checked against official sources on October 22, 2026.
-
Question 1 of 25
Show answer
Answer: B. 50 questions, with at least 45 correct
CITB states the test has 50 questions and the pass mark is 90%, so you need at least 45 correct answers.
-
Question 2 of 25
Show answer
Answer: B. 45 minutes
CITB gives candidates 45 minutes to answer the 50 questions in the Managers and Professionals test.
-
Question 3 of 25
Show answer
Answer: C. Legal and management; health and welfare; general safety; high risk; environment
CITB lists Sections A to E as legal and management, occupational health and welfare, general safety, high risk activities and environment.
-
Question 4 of 25
Show answer
Answer: C. The Black Manager card and the Academically or Professionally Qualified Person cards
CSCS says the MAP test is required for the Black Manager card and the Academically or Professionally Qualified Person cards.
-
Question 5 of 25
Show answer
Answer: A. Within the two years before you apply
CSCS requires the MAP test to have been passed within the two years before the card application.
-
Question 6 of 25
Show answer
Answer: B. No, CSCS says SMSTS is not accepted for a CSCS card
CSCS states that the Site Management Safety Training Scheme is not accepted for a CSCS card, though it can be stored as a record.
-
Question 7 of 25
Show answer
Answer: D. So far as is reasonably practicable
Section 2(1) requires employers to ensure the health, safety and welfare of employees so far as is reasonably practicable.
-
Question 8 of 25
Show answer
Answer: A. A written safety policy and the arrangements for it
Section 2(3) requires a written statement of the health and safety policy and arrangements, brought to employees' attention and revised as needed.
-
Question 9 of 25
Show answer
Answer: A. To protect non-employees from risks created by its work
Section 3(1) requires employers to conduct their undertaking so that non-employees are not exposed to risks, so far as reasonably practicable.
-
Question 10 of 25
Show answer
Answer: A. The director can be prosecuted as well as the company
Section 37 makes a director, manager or similar officer guilty of the offence too when it was due to their consent, connivance or neglect.
-
Question 11 of 25
Show answer
Answer: B. An improvement notice
Under section 21, an improvement notice states the breach and requires it to be remedied within a period that is not shorter than the appeal period.
-
Question 12 of 25
Show answer
Answer: A. A suitable and sufficient assessment
Regulation 3 requires a suitable and sufficient assessment of risks to employees and to others affected by the work.
-
Question 13 of 25
Show answer
Answer: A. When it has five or more employees
Employers with five or more employees must record the significant findings and any groups of employees identified as especially at risk.
-
Question 14 of 25
Show answer
Answer: B. If it may no longer be valid or after a significant change
Regulation 3 requires a review if the assessment may no longer be valid or there has been a significant change, and changes must then be made.
-
Question 15 of 25
Show answer
Answer: B. An assessment covering their inexperience and risk awareness
Regulation 3 bars employing a young person until an assessment covering their inexperience, immaturity and lack of risk awareness has been made or reviewed.
-
Question 16 of 25
Show answer
Answer: D. Arrange how the project is managed, with enough time and resources
Regulation 4 requires the client to make suitable arrangements for managing the project, including allocating sufficient time and other resources.
-
Question 17 of 25
Show answer
Answer: C. Every designer and contractor appointed or being considered
Regulation 4 requires the client to provide pre-construction information as soon as practicable to designers and contractors.
-
Question 18 of 25
Show answer
Answer: C. When there is or is likely to be more than one contractor
Regulation 5 requires both appointments where there is, or is reasonably foreseeable to be, more than one contractor.
-
Question 19 of 25
Show answer
Answer: A. In writing, as soon as practicable, before construction starts
Regulation 5 says the client must appoint them in writing, as soon as practicable, and before the construction phase begins.
-
Question 20 of 25
Show answer
Answer: D. The client must do the principal contractor's duties
Under regulation 5, a client who fails to appoint must fulfil the principal contractor duties in regulations 12 to 14.
-
Question 21 of 25
Show answer
Answer: C. The principal contractor
Regulation 7 passes a domestic client's duties to the contractor, or to the principal contractor when there is more than one contractor.
-
Question 22 of 25
Show answer
Answer: C. Over 30 working days with more than 20 workers at once at any point
Regulation 6 makes a project notifiable if it lasts over 30 working days with more than 20 workers at once, or exceeds 500 person days.
-
Question 23 of 25
Show answer
Answer: D. It is notifiable because it exceeds 500 person days
Regulation 6(1)(b) makes any project scheduled to exceed 500 person days notifiable, whatever the number of workers at one time.
-
Question 24 of 25
Show answer
Answer: A. The client, and it is displayed in the site office
Regulation 6 requires the client to notify in writing before the construction phase and the notice to be clearly displayed in the site office.
-
Question 25 of 25
Show answer
Answer: A. It must not accept the appointment
Regulation 8 says a designer or contractor must not accept an appointment unless they have the necessary skills, knowledge, experience and capability.
Keyboard: 1–4 to answer, Enter for the next question.
The real test: 45 of 50 (90%)
What to know before the test
- The Managers and Professionals test has 50 questions and lasts 45 minutes. You must answer at least 45 correctly (90%).
- The test has five sections: legal and management; occupational health, wellbeing and welfare; general safety; high risk activities; and environment.
- CITB updated the test in June 2023. CSCS says new subjects included mental health, leadership, occupational health governance, behavioural safety and new technologies.
- The MAP test is needed for the Black Manager card and the Academically or Professionally Qualified Person cards. The pass must be from the last two years.
- You can book online through Pearson VUE, by phone, or through an Internet Test Centre.
- Questions in the real test may be worded differently from the CITB revision materials, but they test the same knowledge.
- The Black Manager card is valid for five years.
Frequently asked questions
How many questions are on the CITB Managers and Professionals test?
There are 50 questions and you have 45 minutes. You need at least 45 correct answers (90%) to pass.
Who needs the Managers and Professionals test?
CSCS says it is required for the Black Manager card and the Academically or Professionally Qualified Person cards. Use the CSCS card finder to check your role.
How long does a MAP test pass last for a CSCS card?
For a Black Manager card, CSCS requires a pass within the two years before you apply.
Is the MAP test the same as the operatives test?
No. Both are CITB HS&E tests, but they are different versions. The MAP test is the version for management roles, and CITB says its content is wide and not role specific.
Can SMSTS replace the MAP test?
No. CSCS says the Site Management Safety Training Scheme is not accepted for a CSCS card. You still need the right HS&E test or an approved alternative.
Sources
- CITB: Managers and Professionals test
- CITB: Prepare for the HS&E test
- CSCS: Health and safety test
- CSCS: How to get a Black Manager card
- CSCS: Changes to the CITB HS&E test for Managers and Professionals
- Construction (Design and Management) Regulations 2015, regulation 6: Notification
- HSE: Principal contractors under CDM 2015
- Management of Health and Safety at Work Regulations 1999, regulation 3
- HSE: RIDDOR, when do I need to report?
- HSE: COSHH risk assessment
- HSE: Duty to manage asbestos
- HSE: Construction, work at height FAQs
- Environmental Protection Act 1990, section 34: Duty of care as respects waste