EPA Lead-Safe Renovator (RRP) Practice Test 2026: Practice test 2
Practice test 2 of 3 for the EPA Lead-Safe Renovator (RRP) Practice Test: 25 more questions with answers and explanations.
-
Question 1 of 25
Show answer
Answer: C. Every other time
EPA's renovator training page says the 4-hour refresher must include hands-on learning every other time a renovator takes it.
-
Question 2 of 25
Show answer
Answer: B. Take the 8-hour initial course again
EPA says that if certification expires, the renovator must take the 8-hour course again to become certified.
-
Question 3 of 25
Show answer
Answer: D. Copies of their initial and most recent refresher course certificates
EPA says renovators must keep copies of their initial and most recent refresher training certificates at the work site.
-
Question 4 of 25
Show answer
Answer: B. When signs are posted, containment is set up and cleaning is done
EPA's compliance guide says the certified renovator must be on site while warning signs are posted, containment is set up and cleaning is done.
-
Question 5 of 25
Show answer
Answer: C. Renovate Right
The pre-renovation education rule requires the Renovate Right lead hazard pamphlet to be given out before work begins.
-
Question 6 of 25
Show answer
Answer: D. The owner and the occupants
EPA's guide says to give the pamphlet to the owner and to the occupants before the renovation starts.
-
Question 7 of 25
Show answer
Answer: A. Within 60 days of delivery
The pamphlet can be given no more than 60 days before work begins, so the project must start within 60 days of delivery.
-
Question 8 of 25
Show answer
Answer: C. A certificate of mailing at least 7 days before the work starts
If mailing the pamphlet, the firm must get a certificate of mailing at least 7 days before the renovation begins.
-
Question 9 of 25
Show answer
Answer: B. Use a self-certification of delivery
For tenant-occupied units only, EPA allows a self-certification of delivery when the tenant is unavailable or declines to sign.
-
Question 10 of 25
Show answer
Answer: D. Notify parents and guardians, or post signs about the work
EPA's guide says firms must also send notices to parents or guardians, or post signs describing the nature, location and dates of the work.
-
Question 11 of 25
Show answer
Answer: C. A notice about the work, or posted signs, plus updates if plans change
For common areas, firms notify tenants or post signs, and they must give a supplemental notice if the scope, location or timing changes.
-
Question 12 of 25
Show answer
Answer: C. Their lead-safe certification
Renovate Right advises families to ask to see the contractor's certification and a copy of their training certificate.
-
Question 13 of 25
Show answer
Answer: D. Before the renovation begins
Section 745.85 requires warning signs to be posted before renovation begins, to keep people out of the work area.
-
Question 14 of 25
Show answer
Answer: C. Until the renovation and the cleaning verification are finished
Signs must stay in place and readable until the renovation and the post-renovation cleaning verification are complete.
-
Question 15 of 25
Show answer
Answer: C. In the occupants' language
EPA's guide says to post warning signs in the occupants' language so they understand they must stay out of the work area.
-
Question 16 of 25
Show answer
Answer: A. At least 6 feet, or farther if needed to contain dust
Interior containment requires taped plastic on the floor at least 6 feet beyond the work perimeter, or farther if needed.
-
Question 17 of 25
Show answer
Answer: C. Close them and cover them with taped plastic
EPA's guide says to close and cover HVAC ducts in the work area with taped-down plastic so dust is not spread.
-
Question 18 of 25
Show answer
Answer: D. An impermeable, tightly sealed floor-to-ceiling barrier
The guide allows a floor-to-ceiling vertical barrier instead of floor covering if it is impermeable and tightly sealed.
-
Question 19 of 25
Show answer
Answer: C. At least 10 feet, or farther if needed
Exterior containment means covering the ground with plastic at least 10 feet beyond the work perimeter, or farther to catch falling debris.
-
Question 20 of 25
Show answer
Answer: A. All doors and windows within 20 feet of the renovation
EPA's guide says to close all doors and windows within 20 feet of the exterior renovation to keep dust out of the home.
-
Question 21 of 25
Show answer
Answer: B. Use vertical containment or equal extra precautions
When a property line prevents 10 feet of ground cover, EPA's guide calls for vertical containment or equivalent precautions.
-
Question 22 of 25
Show answer
Answer: B. Open-flame burning or torching
Section 745.85 prohibits open-flame burning or torching of painted surfaces because it creates lead fumes and dust.
-
Question 23 of 25
Show answer
Answer: A. Only with a shroud or containment system and a HEPA vacuum attachment
Power tools are prohibited on painted surfaces unless they have shrouds or containment systems with a HEPA vacuum attachment.
-
Question 24 of 25
Show answer
Answer: A. Below 1,100 degrees F
Heat guns are allowed on painted surfaces only at temperatures below 1,100 degrees Fahrenheit.
-
Question 25 of 25
Show answer
Answer: A. Make sure they, their tools and waste containers are free of dust
EPA's guide says workers, tools and the outside of waste containers must be free of dust and debris when they leave the work area.
Keyboard: 1–4 to answer, Enter for the next question.
The real test: EPA does not publish a question bank or a test format. The accredited training provider runs the course and issues the course completion certificate.